Barwa City

An iconic residential complex in the heart of Doha

  • ETA Engineering - Barwa Commercial
  • ETA Engineering - Barwa Commercial
  • ETA Engineering - Barwa Commercial
  • ETA Engineering - Barwa Commercial
  • ETA Engineering - Barwa Commercial
  • ETA Engineering - Barwa Commercial
  • ETA Engineering - Barwa Commercial
  • ETA Engineering - Barwa Commercial
  • ETA Engineering - Barwa Commercial

Barwa City

Project Highlights

• Around 217,800 sq mts of Duct Work
• Around 160,000 mts of Cable
• Around 14,580 Nos of Fire Fighting Pipe
• 48 Nos of Air Handling Units
• 109821 Nos of Light Fixtures
• 660820 mts of Hot & Cold Water Piping
• 10800 Nos of Fan Coil Units
• 96 Nos of CHW Pump
• 192 Nos of Fans – Stair Case Pressurization
• Around 250,000 sq mts of Duct Insulations
• 130,000 mts of CHW Pipe
• 175,000 mts of CHW Pipe Insulation
• Around 190000 mts of Drainage


  • ETA Engineering - HUAWEI Bangalore
  • ETA Engineering - HUAWEI Bangalore
  • ETA Engineering - HUAWEI Bangalore
  • ETA Engineering - HUAWEI Bangalore
  • ETA Engineering - HUAWEI Bangalore
  • ETA Engineering - HUAWEI Bangalore
  • ETA Engineering - HUAWEI Bangalore
  • ETA Engineering - HUAWEI Bangalore
  • ETA Engineering - HUAWEI Bangalore

HUAWEI TECHNOLOGIES

Client: Huawei Technologies India Pvt Ltd, Bangalore
PMC: M/s Synergy Property Development Services Pvt Ltd, Bangalore
Architect: M/s DSP Design Associates Pvt Ltd, Bangalore
Quantity Surveyor: M/s Langdon & Seah Consulting India Pvt Ltd, Bangalore
Consultant: Power Design India Private Ltd, Bangalore


  • BARWA COMMERCIAL AVENUE PART-1
  • BARWA COMMERCIAL AVENUE PART-1
  • BARWA COMMERCIAL AVENUE PART-1
  • BARWA COMMERCIAL AVENUE PART-1
  • BARWA COMMERCIAL AVENUE PART-1
  • BARWA COMMERCIAL AVENUE PART-1
  • BARWA COMMERCIAL AVENUE PART-1
  • BARWA COMMERCIAL AVENUE PART-1
  • BARWA COMMERCIAL AVENUE PART-1

BARWA COMMERCIAL AVENUE PART-1

Project Description: BARWA COMMERCIAL AVENUE TYPE-1 : ETA Doha is executing MEP works for Barwa Commercial Avenue Type-1 projects. It consist of show room and office complex. 40 blocks and 7 towers (G+3)
Consultant: M/s Maunsell AECOM
Main contractor: M/S. HOCHTIEF
Approximate subcontractor Value (MEP): QR 257 Million


  • BARWA COMMERCIAL AVENUE PART-2
  • BARWA COMMERCIAL AVENUE PART-2
  • BARWA COMMERCIAL AVENUE PART-2

BARWA COMMERCIAL AVENUE PART-2

Project Description: BARWA COMMERCIAL AVENUE TYPE-2 : ETA Doha is executing MEP works for Barwa Commercial Avenue Type-2 projects. It consist of show room and office complex. Total 17 Buildings (Tower-1 3 Nos, 8 Bay -1 No, 7 Bay -13 Nos & 6 Bay 2 Nos)
Consultant: M/s Maunsell AECOM
Main contractor: M/S. HOCHTIEF
Approximate subcontractor Value (MEP): QR 188 Million


  • JAIDHA COMMERCIAL DEVELOPMENT
  • JAIDHA COMMERCIAL DEVELOPMENT
  • JAIDHA COMMERCIAL DEVELOPMENT
  • JAIDHA COMMERCIAL DEVELOPMENT
  • JAIDHA COMMERCIAL DEVELOPMENT
  • JAIDHA COMMERCIAL DEVELOPMENT
  • JAIDHA COMMERCIAL DEVELOPMENT
  • JAIDHA COMMERCIAL DEVELOPMENT
  • JAIDHA COMMERCIAL DEVELOPMENT

JAIDHA COMMERCIAL DEVELOPMENT

Project Description: ETA M&E is Completed its MEP works for Jaidha commercial project. This building consists of 3 basements, ground floor, mezzanine and 7 floors. The building is designed for the purpose of commercial offices
PM & Consultant: MZ & PARTNERS
Main contractor: M/s Multiplex Medgulf
Approximate subcontractor Value (MEP): QR 65 Million


  • AL WAAB CITY
  • AL WAAB CITY
  • AL WAAB CITY
  • AL WAAB CITY
  • AL WAAB CITY
  • AL WAAB CITY

AL WAAB CITY

Project Description: AL WAAB CITY: ETA Doha is executing MEP works for Al waab projects. It consist of open-plan apartments , one and and two storey apartments with sunshade walls of glass, loft units with open bedroom mezzanines, grade level walk-ins etc
PM & Consultant: M/s Cansult / M/s ECG
Main contractor: M/s Arab Tech
Approximate subcontractor Contract MEP Value: QR 210 Million


  • DOHA CONVENTION CENTER
  • DOHA CONVENTION CENTER
  • DOHA CONVENTION CENTER

DOHA CONVENTION CENTER

Project Description: Our Scope of Works include Engineering, Procurement, Installation, coordination of MEP services, and Testing and Commissioning.
PM & Consultant: M/s Turner & M/s Arup & M/s Hyder
Main contractor: M/s Besix – M/s Midmac JV
Approximate subcontractor Value (MEP): QR 430 Million


  • BARWA AL BARAHA
  • BARWA AL BARAHA
  • BARWA AL BARAHA
  • BARWA AL BARAHA
  • BARWA AL BARAHA
  • BARWA AL BARAHA
  • BARWA AL BARAHA
  • BARWA AL BARAHA
  • BARWA AL BARAHA

BARWA AL BARAHA

Project Description: Barwa Al Baraha development is designed to serve as an integrated workers’ city that will
accommodate 53,000 workers and employees, making it the GCC’s largest workers’ accommodation
PM & Consultant: M/s. Qatar Design Consortium
Main contractor: M/s. Construction Reconstruction Eng Co. WLL
Approximate subcontractor Value (MEP): QR 115 Million


RENAULT NISSAN AUTOMOTIVE

ETA Engineering has carried out Electrical Installations at the Automobile Manufacturing Facilty at Oragadam for a value of 60 Crores. The plant has a capacity of 400,000 vehicles per annum. Renault Nissan is a joint venture between Renault India Private Limited and Nissan Motors Japan.


DAIMLER INDIA COMMERCIAL VEHICLES

DICV is a subsidiary of German Daimler AG. This company designs, manufactures and sells commercial vehicles that cater to the demands of Indian customers. DICV choose ETA to carry out their MEP Services at their Oragadam plant for a value worth 40 crores.


ALLISON TRANSMISSION

Electrical works for state of art manufacturing facility of Allison Transmission, a US based company, who manufacture the broadest and most advanced range of fully automatic power shifting transmission for on and off road application. ETA Partnered with Allison for their entire Electrical scope of works for a total value of Rs. 10 crores.


ASCENDAS IT PARK

Ascendas is a major facility provider with their HQ based in Singapore. For their new IT Park in Chennai, ETA has been chosen, fora Design & Build Package, having a total AC load of 2100 TR and 7500KVA Electrical load, at a value of approx. INR 33 Crores. It Started with Phase I and ETA secured a strip of orders for all MEP works at their campus for a value of INR 20 Crores.


NOKIA MANUFACTURING FACILITY

Nokia Manufacturing Facility has chosen ETA Engineering to carry out the Electro Mechanical work at their Sriperumbudur (Chennai) Unit. 2000 TR of HVAC work and 11200 KVA of electrical work completed as a fast track project “TO EXACTING INTERNATIONAL STANDARD” for a value of INR 23 Crores.


ABU DHABI COMMERCIAL BANK

Client: Abu Dhabi Commercial Bank
Consultant: M/s. Architecture & Planning Group
Project Management: M/s. Turner Construction International
Contract Duration: 18 Months


NATIONAL BANK OF ABU DHABI

Client: National Bank of Abu Dhabi
Consultant: Architecture & Planning Group
Project Manager: CRSS, INTERNATIONAL INC.
Main Contracor: Al Habtoor – Murray & Roberts JV
Scope of Works: Electrical and Plumbing Services
Contract Duration: 24 months


FIRST GULF BANK

Client: First Gulf Bank
Project Manager: M/s. The Morganti Grup Inc.
MEP Consultant: AM/s. The Salaam Consultants
Main Contractor: M/s. Emirate Belbadi Contg. Co.
Date of Completion: JULY 2004
Duration: 10 Months


COMMERCIAL BANK OF DUBAI

Client: COMMERCIAL BANK OF DUBAI LTD
Consultant: M/S. THE FASER, NAG PARTNERSHIP
Main Contractor: ASSOCIATED CONSTRUCTIONS (ASCON)


ONGC HEAD QUARTERS

Owner: ONGC
Main Contractor: Pratibha Industries Ltd
Contract value: INR 33Crores
Project Start Date: Sep 2011
Scope: Depot MEP Services, Air-conditioning, Ventilation, Electrical System, Plumbing System & Fire Fighting System


VODAFONE DATA CENTER

Owner: Vodafone
Contract value: INR 105 Crores
Project Start Date: March, 2013
Special Feature: Asia’s Largest Tier -IV Data Center
Scope: M & E, Low Side Air Conditioning & Ventilation System, Low side Electrical System